Client: JSC TNC "KazChrome" (ERG CP)
Location: Aktobe region, Kazakhstan
Period of work: June 2020 - May 2021
Description of works:
Client: RG Processing LLP
Location: Akmola region, Kazakhstan
Period of work: May 2020-December 2020
Description of works:
Design and survey work (basic design), including:
Client: KAZ Minerals, Aktogay LLC
Location: Ayagoz district, East Kazakhstan region
Period : 2018 – current
Scope includes:
Plant Infrastructure, including:
Client: Karabatan Utility Solutions
Location: Karabatan, Atyrau region, Kazakhstan
Period: 2018 – current
Scope includes:
Client: TNK Kazchrome (ERG)
Location: Aktobe region, Kazakhstan
Period: October 2018 - May 2020
Scope includes:
Replacement of conveyor systems of PC No. 4 of Aktobe Ferroalloy Plant:
Client: KAZ Minerals
Location: Ayagoz district, East Kazakhstan region
Period: October 2018 - May 2020
Scope includes:
Client: KAZ Minerals
Location: Ayagoz district, East Kazakhstan region
PERMANENT CAMP PROJECT (II)
PERMANENT CAMP PROJECT (I)
Client: Tengizchevroil LLP
Location: Tengiz, Atyrau region
Period: 2018 – 2020
Scope includes:
Pre-fabricated fully welded substation building with integrated free-issued equipment
Client: Karachaganak Petroleum Operating B.V.
Location: Karachaganak, Burlinsky district, WKO
Period: 2018 – 2019
5 Enclosures with Electrical Distribution Systems
Scope includes:
Pre-fabricated fully welded buildings with integrated free-issued equipment
Location: Karasai district, Almaty region, Kazakhstan
Period: 2015 – 2016
The plant was designed and built in-house by PSI, taking into account the high standards and requirements for servicing large international projects in the country and meeting the needs for the manufacture of high quality steel structures.
Kazakhstan content 100%
Productivity 18,000 t / y